All the utilities were roughed in by the middle of the week, which to our surprise, was well ahead of schedule. Also to our surprise, the insulation crew came in right behind them to fill in the walls with fluffy, pink fiberglass insulation. The insulation crew also installed the vapor barrier by week's end.
Again, since crew's were busy inside, the carpenters were outside working on the front porch ceiling, decking, wall shingles, and trim. On Friday, the lumber for the back deck was delivered.