Friday, June 6, 2008

Week 18



Yeah, I missed week 17 as far as photos go. This week, all the work was primarily done by the blue-board and plaster crew. first they hung all the wall board, followed by prep work (taping, etc.), and then finally skim coating all the walls and ceilings with plaster. These guys cause a great deal of mess, but luckily they cleaned up well after themselves.

Week 18 the painters rolled in; put on a prime coat and one finish coat. Also, most of the interior window casings and sills were stained. Plumbing fixtures are now delivered and will sit in the basement until ready for installation. Rear deck is complete and ready for the first barbeque. My blog posts are still short as I just try and get caught up :-)